P1666 Schedule as of Dec 16,
2004 |
|
| Owner |
By Date |
Task |
Notes |
|
|
|
|
| |
9-Aug-04 |
SG organization meeting |
done |
| |
18-Nov-04 |
Nescom vote to approve PAR |
done |
| |
16-Dec-04 |
Hold Organizational Meeting |
done |
| |
16-Dec-04 |
Complete P&Ps |
done |
| |
7-Feb-05 |
Draft Invitation to Ballot |
|
| |
7-Feb-05 |
Review Invitation to Ballot |
|
| |
10-Feb-05 |
Finalize Invitation to Ballot |
|
| |
15-Feb-05 |
Issue Invitation to Ballot |
|
| |
28-Feb-05 |
Receive draft LRM |
|
| |
30-Mar-05 |
WG complete review of draft |
|
| |
15-Apr-05 |
Complete 2nd draft LRM |
|
| |
15-Apr-05 |
Finalize Balloting Constituency |
|
| |
15-Apr-05 |
Prepare Ballot cover letter |
|
| |
15-Apr-05 |
Approve Ballot cover letter |
|
| |
30-Apr-05 |
Complete review of 2nd draft |
|
| |
1-May-05 |
WG approves 2nd draft LRM |
|
| |
1-May-05 |
Initiate Balloting process |
|
| |
30-May-05 |
Collect all ballot responses |
|
| |
15-Jun-05 |
Resolve negative ballot comments |
|
| |
30-Jun-05 |
Complete 3rd draft LRM |
|
| |
30-Jun-05 |
Prepare cover letter for 3rd draft |
|
| |
30-Jun-05 |
Prepare summary of negative ballot resolutions |
|
| |
15-Jul-05 |
Recirculate 3rd draft with resolutions |
|
| |
30-Jul-05 |
Collect recirculation results |
|
| |
5-Aug-05 |
Create final submission to RevCom |
|
| |
10-Aug-05 |
Approve final submission to RevCom |
|
| |
12-Aug-05 |
Submit to RevCom |
|
| |
20-Sep-05 |
RevCom approves P1666 |
|
| |
21-Sep-05 |
Standards Board approves P1666 |
|
|
|
|
|